How to test a newly configured change request management at SM7.0

Former Member
0 Kudos

Hi!

We have just finished the change request management at SM7.0.

This is done for only one landscape (DEV ->QA ->PROD) for the proof of concepts.

Could you provide a procedure to test it?

Thanks a lot!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Jennifer,

Try transaction "/n/tmwflow/charmchk".

Before trying this transaction, create a maintenance project and activate change request management for that project.

It will chk all the configurations and will summarize about the successs or failure of your configurations relating to CHARM.

best regds,