on 06-04-2008 7:10 PM
Hello,
Is it possible to create production order without planned order(from MRP) and without Routing. Can anybody give the sequence of transactions.
very urgent and helpful answers immediately rewarded.
vps
Hi vps
You cannot create prod order directly through MRP run.
MRP run will create either PR OR Plan order first then only prod order / purchase order can be created by conversion.
If you want to create prod order without plan order. Create it manually through CO 01
Creation of prod order without Routing is possible. But you should have default operation.
At the time of creating prod order. The system will display no task list selected. Either cancel or select operation. You should select default operation.
Hope this is clear
Regards
J . Saravan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can create production order without planned order using CO01, CO07 and CO08.
You can create production order without routing by doing setting in OPL8.
Regards,
Alok Tiwari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can create production order without planned order by CO01 but not without routing.
PP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In standard SAP here are the Tcode to create Prod Ord without MRP rus.
CO01- with material
CO07-without material
CO08-for sales order
CO10- for project(For PS)
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
yes you can do production order without MRP run..with help of T code Co01
co08 and co10 according to ur company business ,when u will save the production order automatically it takes activity type 10 for the scheduling..and u have to put all components manually which u have used in BOM..
i think this is essay way for u
Regards
aqueel
Hi,
If you have assigned strategy group as 82 then you can
create a Production order if you create a sales order.
Even without routing you can create a Production order
but for this you need to define default operation for your
order type.
Regards,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you have assigned strategy group as 82 then you can
create a Production order if you create a sales order.
Even without routing you can create a Production order
but for this you need to define default operation for your
order type.
Regards,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can directly (manually) a production order without reference to a Planned Order (from MRP) and also without a routing in CO01 , provided you do the following settings.
1. In OPL8 -Planning tab page -Routing tab ( for the order type you are going to use in CO01)
set the Routing selection to 0 - No routings or reference operation sets to be used.
2. In OPJG , do the settings for the same order type. ( for default values generation of operations )
Now you can create a prod order in CO01
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can drectly create a production order by using
CO01( with material)
CO07( with out material)
CO08( for sales order)
But with out routing Not possible, either you need any of these two task list to create a production order.
1. Routing or
2. Reference operation set
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You can create Prod order with Planned order or MRP the 2 functionalities are only needed when you are using them. Just go to Co01 enter material plant and order type and proceed with the creation.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes, you can create prod order without planned order and routing . Create it manually using t.code "co01".
Please come back in case of proble.
Regards,
satyajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.