Maintenance cost center and Production cost center

249 Views

Hi Gurus,

We defined various cost centers in master data like General Production,Waste water,Piping etc...Also in Workcenter we tie up with maintenace cost center which is totally different from master data.

My question is...if we write a work order for particualr equipment where cost center may be 0111-2000 and using the work center has 0222-2003 (maintenace cost).Where the cost will get reflected ?

Whether it goes to the master data cost center or the cost center tied up with workcenter.If it goes to WC then what about if we use multiple WC for different operations?

Also if we reserve spare parts for tht work order where the cost of the spart part will go and sit ?

I am really confused about the maintenance cost and cost against WO.

Please advice.