Hi Experts,
One of the users in our client is creating a purchase requisiton manually.He is not entering the delivery date in the item overview. But, the system is taking a release date which is not today's date and then calculating the delivery date considering planned delivery time and purchasing processing time.
My questions is where from the release date is defaulted?
This release date is varying from material to mateial.
Thanks in advance