cancel
Showing results for 
Search instead for 
Did you mean: 

Conversion of Planned order into a Production Order.

Former Member
0 Kudos

Hi All,

I have one ticket in which I have to change the format of generating serial no.s.This format has to consider

Basic Start Date while generating it.In our project Serial No is getting generated at the time of Production Order.

So I have to pass this start date before Prod Order is getting created from a Planned Order.What i want to know is it possible to pass a start date when a Planned Order is getting converted into Prod Order as i think it will be a standard SAP program which will convert a Planned Order into Prod Order.Any suggestions on how to achieve this is most welcome.

Thanks in Advance,

Saket

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks for all help.

Former Member
0 Kudos

Hi,

I am not able to get what is passing the start date.

Second thing is how you are generating the serial number - manually or automatic?

If you are generating serial number automatic, then it is not possible to generate it considering the basic start date.

But if you are entering the serial number manually, then there should not be any problem as system will accept that serial number which you enter at the time of conversion of planned order to production order.

Regards

Amit parkhi

Former Member
0 Kudos

Hi,

it is not possible to pass a start date when a Planned Order is getting converted into Prod Order.It will be passed only after the production order is saved.Because the serial number should pertain to a product and the production order in which it is manufactured, so that a start date and serial number willl be passed against that prod. order.

With Warm Regards

Ravindra