BOM components in Production order getting multiplied

while creating a production order the bom component for the material is getting multiplied by 1000; even though the requirement is generated for one component in production order.

What could be the possible reason for this ? Can anyone help me in this situation?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 31 at 10:23 AM

    Hi Anukool,

    Please check the base quantity of the BOM, which was picked by the production order (you may see this information in the production order on the master data tab).

    Regards,
    Mate Lisztes

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 31 at 10:41 AM

    Hi Mate,

    Already did that, actually this process is related to kitting, and this is happening at the time of generating dekit orders.

    Thanks