Former Member
Jun 03, 2008 at 03:07 PM

Query on resource selection condition

46 Views

Hi All

I have a process order with a operation having a resource selection condition.In the classification of the master recipe i have entered the resource name(as characteristic value) as X whereas the name of the resource where the operation is to take place is A and in the classification of the resource A i have enter the characteristic value as "A".

Now is it possible to release the process order without getting the error message :"Resource in operation does not satisfy resource selection condition".

please advice.