Skip to Content
0
Former Member
Jun 03, 2008 at 10:42 AM

PM-PP integration

21 Views

Hi all,

Our client has PM module implemented. They procure some material for plant maintenance purpose. But they do not use the material straight away. They cut that material to pieces and galvanise them and use them in plant maintenance. All this work is done in-house. They want to capture this processing cost incurred on this material i.e., cutting and galvanising. Can this cost be captured directly in PM module or it is to be captured through a Production order?

Thanks in advance

Regards,

Ram