We have the plan to upgrade our solution Manager 7.2 from 7.1 in sybase db.

In solution Manager 7.2 MCOD is not supported.

How to split Abap & Java system and how to do the activity step by step.

Please help us to start procudures wise as per the priority

Regards,

Sithanandan

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Victoria NORMAND
Jan 29 at 10:44 AM
0

Hello Sithanandan,

I moved your question to Software Logistics as primary tag.
You may check the Guides for Dual Stack Split Guides. As mentioned there:

"The split procedure is valid for:

● Optional splitting of SAP NetWeaver dual stack-based systems (such as SAP BW systems with SAP BEx Web) and SAP Business Suite systems based on SAP NetWeaver 7.1 and higher.
● Mandatory splitting of SAP NetWeaver dual stack-based systems upgraded to SAP NetWeaver 7.5 Process Integration or SAP Solution Manager 7.2.

"

Check the Split Option "Move your Java Database".
HTH,
Best regards,
Victoria.