My user have created one project, In that there are various levels WBS Elements.

Normally we never tick Level One WBS Element as a Acct Assignment Element.But User have made Level One WBS Element as Acct Assg Element and then Project is Released.So now I can't remove that tick because that field is Grayed out or Freezed.

Now i wanted to Remove or Undo Release status and then I have to remove Acct Assg Element Tick.

Pls guide me on this issue.

Thanks in Advance.