Hi Gurus,
While creating Pull list for particular material xxx, in the dependent requirements of yyy system is showing one MRP element NProc. Which is also participating in the Net Requirements calculation for the Storage Location & for this Dep Req we are unable to find Header Requirements.
This particular requirement is not getting deleted even after the MRP run & even cannot be deleted manually.
What is the MRP element Nproc?