General Rule in WBS

I have red an article saying that "As general rule, all LEVEL 1 WBS ELEMENT of a PROJECT will be the PROJECT DEFINITION and DESCRIPTION". Why and what is the significance of this?

TIA!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 30 at 12:03 PM

    Hi,

    There is no standard rule, you can use different coding. Since you need to do validation in case if you want Project and Level 1 WBS element same.

    The signficance for the Uniformity in the project and ease for reporting.

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 31 at 01:47 PM

    Hi,

    I would say the significance is about PS/IM integration. It makes it really nice and easy the scenario of a single WBS at level 1 with a code same as PD code.

    Regards,

    Paulo