I have a scenario where one product---- P1 in manufactured on resource A.

If , there is no capacity with resource A , then it can be manufactured in resouce B.

As per my knowledge , We can maintain alternate resource.

I also want to know how maintain the priority for uasge of the resource.

I want to maintain highest priority for usage of resource A , if A

do not have the capacity then resource B should be used.

Please let me know How to maintain an alternative resource and priorities for the resources?

Please give the tcode.

I am working with PDS in PP/DS.

When The planner will do planning of the product P1--- on resource A , Then he will get a -- Alert for capacity not available.

Then he will execute the planning with alternate resoure B.

Waiting for your answers.

Regards,

Ravindra

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jun 02, 2008 at 10:38 AM

    Hi ravindra

    Pls execute the following steps

    1) Create Work center - say for ex R1

    2) Create another Work center say R2 which is alternate to R1

    3) Create Charcterstics for Alt resource

    4) Create a class using classification type 019

    5) Asign the charcaterstic to Class

    6) Assign the class to the R1 work center. When assigned, a pop window is disaplyed for selecting the alternate work center select the check box for alt work center

    7) In the routing for the operation where u r assigning the R1 work center - assign the same class which is created. For this go to Extras Menu and choose classification and also u can select the work center as alternate

    8) CIF charcterstic and class to APO

    9) Cif Material Master

    9) Cif all work centers R1 and R2

    10) CIF PDS, both R1 and R2 will get transfterred and R2 will be transferred as ALternate resource for R1

    Pls look at the PDS and ensure the priority is set accordingly what is reqd

    Hope this helps

    regards

    Vijay

    9) CIF cl

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.