Control of WBS in network

Hi,

Question 1 : We have around 10 WBS under a project.

Ans Users are creating 2 or 3 networks for each WBS.

i.e for a project there are totally 20 to 30 networks. How to control it?? Is it possible to control my whole project with a

single network??

Question 2 : In the current scenario of the above, my users are using, for example: "WBS.A" in Assignments Tab -> WBS Elements & "WBS.B" inside the Activity Elements. How to control it?

Expecting reply.

Regards,

Deepa

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Jun 02, 2008 at 07:45 AM

    Hi

    >

    > Question 1 : We have around 10 WBS under a project.

    > Ans Users are creating 2 or 3 networks for each WBS.

    > i.e for a project there are totally 20 to 30 networks. How to control it?? Is it possible to control my whole project with a

    > single network??

    Yes its Possible, by not default but by creating the Network at the top level WBS element and then adding the activities to that Network and later picking and droping them to the relevent WBS element.

    > Question 2 : In the current scenario of the above, my users are using, for example: "WBS.A" in Assignments Tab -> WBS Elements & "WBS.B" inside the Activity Elements. How to control it?

    >

    Not sure about this question please reframe it.

    Thanks..

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Sir,

      Thanks for your reply.

      For Ans-1

      - My network is becoming very very slow, if i assign as you say.. Is there any ways to increase my speed of that Single network?

      My Question-2 Again :

      - My project structure as follows

      PS-0201 - Main project

      PS-0201.A - Articles under A

      PS-0201.B - Articles under B

      If we are creating a network for PS-0201.A, Users should not use any other WBS for that network,

      but in system there is no control for that, users are free to change the WBS under activity level...

      Pls. suggest

  • author's profile photo Former Member
    Former Member
    Posted on Feb 24, 2009 at 01:43 PM

    yes

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.