cancel
Showing results for 
Search instead for 
Did you mean: 

Schedule line

Former Member
0 Kudos

Good morning sapiens

I am running a normal cycle in which I have uploaded 100 good quantities at storage location by 561 movement type for make to stock scenario.

Now when I am making sales order and I am going to schedule line it is automatically taking confirmed quantity as zero.

So I can not make its delivery

Plz reply with relevant answer...

Thanks

Tushar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI,

Please check the configuration settings in the IMG for Availability check.

You check have maintaining availability checking group 01 or 02 in the Material master.

Have you assigned Checking rule AE -SD order; make-to-order stock for checking group 01 or 02 in the IMG

Spro>sales and distribution>Basic functions>Availability check and transfer of requirements>Availability check>Availability check with ATP logic/Against planning>Carry out control for availbility check.

I hope it will help you,

Regards

Rahul

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Go to the same sales order..... click on item availibility check ico or press control F4 or go to EDIT option on the top and select item avalibility check. then go to schedule line and see the confirm qty with schedule date and make the delivery on the same date.

hope this will help u

Regards,

Jay

Lakshmipathi
Active Contributor
0 Kudos

Dear Tushar

Go to VOV6, select your schedule line category and click on magnifying lens on top so that it will take you to a screen where select the field "Availability". Now retry so that the quantity will be confirmed in sale order.

thanks

G. Lakshmipathi