on 06-02-2008 2:09 AM
I tried to enter a budget into SAP. So far, so good. But when using this Cost Center I get the following error message:
"Enter rate NZD / AUD rate type P for 01.04.2008 in the system settings"
How can I correct this?
Markus
Hi,
Use T.code: OB0(Zero)8 i.e OB08 and maintain Exchange rate type for P for NZD/AUD rate from 01.04.2008.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I can't find that NZD/AUD rate for 01/04/08.
http://www.siteupload.de/p767919-clipimage002jpg.html
And can you give me the wohle path to OB08.
Markus
hi
goto img-> my sap erp->general settings->enter exchange rate
give exchange rate type as p and give the values.
hope this will help u
regards,
sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Markus,
When there is no entry in trx. OB08 then you have to maintain such an entry wikth button 'New entry' for exchange rate P currency NZD / AUD.
IMG (Implementaion Guide) can be found under trx. SPRO. In trx. SPRO you can do all your customizing settings. In R/3 you will find the currency customizing as follows:
SPRO --> General Settings --> Currencies --> Enter exchange rates (OB08)
Cheers,
Daniela
Edited by: Daniela Kallenbach on Jun 6, 2008 4:28 PM