Hi All,
I have come across one problem where PIR gets consumed against the internal delivery (VL10B).
When I make delivery against the STO from plant B (where PIR Maintained) to plant A (Where STO created) system consumes the PIR in plant B against the delivery. I am using Strategy 40 in plant B.
I knew that when you make the delivery against the customer order system consumes the demand. By this logic systme is consumed the PIR against the internal del. But my client doesn't want this. They want system should consume the PIR only against the Customer order and not against the del which they make against the STO.
Pls let me know is it possible?
Waiting for your positive reply.
Regards,
Alex