QM Order - Activities confirmation - "Actual values" are not coming in front of activities

amrutarane
Explorer
0 Kudos

I have used Order type QL01 to capture appraisal costs and created following master data -

- I have assigned QM work center to inspection operation and maintained Std. times for the operation of inspection plan.

- Assigned cost center to QM work center.

- Assigned formulae to activity types to calculate the cost in Costing view of the QM work center.

- Created the order manually in QK01 and assigned it to the material. Used the same cost center here.

I am getting the following issues -

- After result recording, I am getting pop-up for activity confirmation but the "Actual values" are not coming in front of activities. The actual value fields for all the activities are coming blank.

I want the actual values to be calculated by the system should be proposed for confirmation, just like it happens in CO11N for production activities confirmation.

is this possible in std SAP for QM order?

Do I have to do development for this?

Accepted Solutions (0)

Answers (0)