Material Availability check on Saving Project:

Dear Experts,

I have a requirement that reservation should not be saved if the material is not available in Stock while adding the material component to a network activity. In Material Master i Have Assigned : Availability check: 01.. In check rule, In availability control, I maintained the following configuration. In Order Control, I maintained check Material availability while saving.and check Status also for Availability check 1 and 2. But this seems not working. Availability check was not carried out while saving the project.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 01 at 04:36 AM

    Hi Sangeeth,

    Refer below link, this is for Maintenance order, you can change the Order type for PS and check.

    https://blogs.sap.com/2016/03/15/material-availability-check-in-maintenance-order/

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 01 at 11:35 AM

    Hi Maria, '

    Thank You. I was able to complete that successfully. I did as per your blog. Its working fine..If the Activity is released and i add a material component, the availability check is not working it seems. I dont want the reservation to be open if the material is not available in Stock. Any enhancement possible.

    My requirement is to prevent the creation of Reservation if the material is not available.Even if the reservation creates, the availability check should work. Kindly suggest any enhancements.