Hello Gurus, we are having an issue in our production system which I'm not able to reproduce in our Q environment for further testing.

Sometimes a PR is created, and funds are reserved for that PR, later a PO is created from that PR, but we have no funds!

I checked the movements in FMRP_RFFMEP1AX and I see the original document with the funds assigned to the PR, and then a Reduction for the same amount, and that's it. The PO can't be saved because it lack of budget for that Commitment item/Fund center combination.

We have tried to fix the PR, PO and budget document using FMN3N, FMN4N and FMN5N with no result.