Skip to Content
0

How to update measuring document through production order confirmation

Jan 29 at 07:20 AM

75

avatar image
Former Member

Hi all of you.I am working on my first implementation of SAP PM.I am facing an issue which is somewhere related to PM-PP Integration i guess.The client has a requirement that when a production order is confirmed with a certain quantity,an updated measuring document should be automatically created with that quantity.For meeting the requirement i had gone through many posts online to check how can i meet the requirement.I had done following things like

1-creating PRT equipment

2-Filling all the required data in PRT TAB

3-Creating measuring point and assigning it in PRT TAB. etc

4 - But still after confirming the PP Order I am not getting a hit on measuring document.

Kindly help please

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

avatar image
Former Member Jan 30 at 09:38 AM
0
Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Jan 29 at 09:06 AM
0

Please refer the below thread.

https://blogs.sap.com/2016/02/12/pp-module-and-pm-module-integration-for-tracking-the-usage-value-of-prts/

There are many discussions happened for this topic.

Share
10 |10000 characters needed characters left characters exceeded