Hi Friends,

When end user is performing reconciliation process (FBICS3), he is getting error 'Process 003 is not active. Complete customizing before starting program.'.

Thanks,

Mark

Accepted Solutions (1)

Accepted Solutions (1)

former_member188826
Active Contributor
0 Kudos

Have you applied the note 863630?

And the following notes also indicate several program errors being fixed.

1071510

1150191

1159776

1078228

1138225

1154899

Former Member
0 Kudos

Hi Sridhar,

This is working fine in DEv and QAS. It is giving error in Prod.

Mark

former_member188826
Active Contributor
0 Kudos

Try to perform client comparison with the help of basis, like using SCU0 may be?

Answers (1)

Answers (1)

Former Member
0 Kudos

Still in progress

Former Member
0 Kudos

This customizing is transported using workbench requests. Did you check with your basis team if there are any errors in the transport log? Any post-processing after import that failed in prod. system?

Former Member
0 Kudos

Hi Srikanth,

I have created new transport. Basis will not help on this issue as this is post go live issue. Thanks for your feedback