on 05-30-2008 7:10 AM
Hi Guru's
I want ot revert the release indicator in my po. i tried with me29n and me28. But, when i am trying to do that , i am getting the message " No new release indicator can be determined"
so i am unable to do the de release indicator for that po.
I checked all relese strategies with release group. there is no problem in setup.
Please any one can help me, this is urgent.
Thanks in advance
Best regards
Laxman
HI,
First check the if the characteristics are defined Properly and then see to that the class contains these characteristics and is used in the release Stratergy.
Then check for release stimulation if the stiulation is working according to the bussiness needs.
Now pick one stratergy check the values and create a purchase Order. It is not necessary to go to ME23N to check if it activated or not. after creating the PO click on Check icon and then after doing this if releases stratergy is applied the tab on the header node will show up.
Thanks & Regards,
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kiran
Thanks for reply. Purchase order already with release indicator. there is no problem in release strategy.
i want to do cancel the release indicator then only i can change some values. for changing purpose i want de release the po. so i am trying for that with me28 and me29n. but, i could not do that. i am getting the message i mentioned in thread
pls do something if u have any idea
Regards
laxman