cancel
Showing results for 
Search instead for 
Did you mean: 

third party issue

Former Member
0 Kudos

hi

i created one third party sales order with material X and Plant 001 , than one PR is genrated automatically , now with refrance to this PR i created one PO , and did MIGO ..

Now i want to change plant in sales order and also want to add one more line item .

ex.

material X with plat 002 and

material Y with plant 002

now what i need to do for same keeping same PR and PO.

( i dont want to create new PO )

thanks

ravikant dewangan

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

As you have processed the first line item fully... created PR, then PO and MIGO also... If you add another line item it will create another PR, if it is third party material (TAS). You will not be able to combine the new line item into the earlier PR and PO.

Prase

Former Member
0 Kudos

hi

as you told sales order should genrate new PR but it is not happing and as i mentiond that i have to change the plant of first line item too .

is there any way so that i can revers the document flow and do the modification

thanks

ravikant dewangan

Edited by: Ravikant Dewangan on May 29, 2008 8:41 PM

Former Member
0 Kudos

Try cancelling the GR and reverse see if that helps

Thanks