Hi,
When i assign quantities to the same production line, the "production start date" is always load for the earliest start date.
Example:
When I assign quantities of 2 differents materials in the same production line. The production start date beguin always at the 6h like if we can produce these materials at the same date.
Hi,
Check the SPRO setting OPU5 - Schedule Planned Order.
Make necessary changes in Adjust Scheduling tab.
You will get the desired result.
Srini