Hi,

Is it possible to set a task duration to less than 1 day?

We are currently using Microsoft Project for some of our project managements and are shifting over to SAP cProjects 4.0. The problem is that many of the tasks in our projects take less than 1 day to complete, and they build up 70% of the WBS, and in cProjects we are unable to set a tasks duration to less than 1 day, giving us a completly overgrown project schedule (month's instead of days).

Thanks!