Cant dispatch a production order to shift number two in CM21

0 Kudos

Hello guys

In CM21 I try to dispatch a production order to shift numer two instead of number one. It doens't work. I'm only able to dispatch the order to shift one, not shift two or three.

Any suggestions.

Br

Fredrik

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Maybe there is no space forward to allocate all those orders. Try to set the flag "changing planning direction" and then try to dispatch again.

Regards,

Caetano

0 Kudos

Hello

Thanks for your respond! I have checked and there are 100% availble capacity in the upcoming weeks. I set the flag but there where no diferrence, I don't get it why I cant dispatch on shift 2 or 3 just shift 1.I have ckecked the work center and can't find anything wrong with them. The system reacts like there are no acapacity availible in shift 2 and 3 but it is. The only way is to set the flag planning in non-working days, but that's not an answer to my problem.

Do you have any more suggestions what I could do?

Br

Fredrik W