How can we assign two paid break sched to One Work Sch?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

just give the break schedule name as same and in serial no give 01 and 02 when you assign this break schedule. both will be picked up.

regards

nalla

Answers (2)

Answers (2)

Former Member
0 Kudos

hi

we have to create breaks in table name" V_t550P

in which we can create many breaks by giveing a four digit character name like

grpg break no start end p paid unpadi

01 1023 01 08:00 08:30

01 1023 02 12:00 12:30

like above u can create n number of breaks

in daily work schedules assign 1023

all the best

madhu

Former Member
0 Kudos

You can not add two break schedules to one work schedule.

Why do you want to do it, what is the scenario. First let us know that. Then we can give the suitable suggestion.