Using Standard Template in Project characters not replaced in new project

Jan 25 at 10:29 AM

22

avatar image

Hi,

I have created a coding mask -XXXXXXXXXXXXXXXXX-XXXX and I have created

a standard wbs template using that coding mask A-MOD000000000000AT. when I create a new project copying this template with project definition A-DT.ISMA.RE.PET.30

only the project definition has its characters replaced with the name of the project. The WBS' created still carry the characters in the standard template ie

A-DT.ISMA.RE00000AT-AATT

Is it possible to have the characters of the WBS replaced when creating a new project ?

This issue doesnt occurs when I use other standard template with coding mask -xxxxx-xx If I create a new project copying this template the characters of the WBS was replaced

Thanks in advance

Flora

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Jan 29 at 08:27 AM
0

Hi Flora,

Just Check whether any Substitution rule was created for copying the project name to WBS element for other project ID

Regards

Terence

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hi Terence,

Thanks for your reply.

I have implemented cnex00033 and worked ..

So, all issue have been resolved ..

Thanks

0

Good. Thanks for the information

Kindly close the thread

Regards

Terence