Hi gurus,
We are using ECC 5.0
The case is there are two types of PR ( NB,MRP) and were assigned to the same source , a contract, in ME56. We want to realize that after ME59 there is one PO created that covers these two PR.
According to our test,there are two POs created accordingly.
Any solutions?
Thank you!