on 05-28-2008 6:34 AM
I have created a local contract in SRM.
However, the materials do not take the price from contract.
The SC take the price in zero when they are created directly in SRM, and the transferred ones of ECC take the price from backend.
some suggestion to solve this issue?
what is yr tech scenario?
classic or ECS?
you are using local or backend products?
If SC is created with backend products
and tech scenario is CLASSIC with backend pur grp responcible
then if a valid ECC contract is available for the SC product
and source list is maintained for the plant and material in ECC
SRM picks up the ECC contract as source of supply
what is yr requirement?
BR
Dinesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry.
I need to create direct PO from contracts, assigning supplier and price of the contract.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dinesh.
I have SRM 5.0 Extended scenario and ECC 6.0.
The local contract is create in SRM and don't exist in the backend.
The materials was create in backend system and envoys to SRM.
Regards.