on 05-28-2008 6:17 AM
Hi all Pp gurus,
Can u please help me in this issue.
Why we have to maintain MRP distribution key? and
what is the impact of this key in splitting of lot size quantity?
Hi,
Is this wrt Rep Mfg?
Regards
Trin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you enter a distribution function for a component, portions of the dependent requirement are distributed over the runtime of the planned or production order in accordance with the distribution function. This means that dependent requirements are not available in full on the order start date. Instead, they are brought into the production process continuously between the order start date and the order finish date.
However, the last portion of the dependent requirement must be available at the latest on the finish date of the assembly.
Regards
Trin
If you want to distribute the Capacity Requirements over a period of time , you can use distribution key.
It is a combination of the Distribution strategy and Distribution function according to which capacity requirements are distributed over the duration of an operation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.