on 05-28-2008 5:04 AM
Hi,
How can I check the MAP of the project stock, which has been GR with "Q" category in PO via WBS element.
I heard the accounting view of material master only for normal stock, so qty and value of project stock would not be updated in that tab, is that true?
Please advise, many thanks in advance.
Regards,
Hi
If you want to valuate the project stock differently apart from the usual stock you need to maintain the Valution class for the Project stock in the Account ing view of the Material master.
For the Valuation class you can assigne seperate G?L accounts also in customizing of account determination
Thanks & Regards
kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks, i think the standard material master accounting view not for project stock.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In my opinion, accounting view will show you reqd details. have alook at tcode MBBS: It may be helpful.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.