Dear all PP gurus,
Can anybody gives me the reason and solution for this issue.
its a very urgent.
Split in lot size quantity of Material during MRP run.
Lot size for material xyz and plant is abc
Lot size is FX Fixed order quantity.
Fixed lot size 84.000 KG
But during MRP run system split the material quantity as 16.800 X 5 = 84.00 KG