Position Assignment issue with A008

Former Member
0 Kudos

Hi Experts.

I have a problem of assigning more than one person in a position

In the config i give A008 relationship with 3 as time constant

and while assigning person i am using assignment percentage

like.. 50 % and 50% for 2 persons. it is working but it allows more the 2 persons with 50 % assignment .

So i thing there is no check on the Percentage field.

please let me know the config. how to restrict the position with 100 % with any no of person.

Thanks..

Avik

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Avik,

you can achive this by maintaining 100% as E(Error) against relationship 008 in table T77AR,

otherwise it wont check the 100% occupancy.

Regards,

Soori

Former Member
0 Kudos

Hi Soori ,

Thanks...

I already did that in T77AR table with rel 008 - E in 100% check field.

B 008 Holder E E E

but i am not doing for A relationship means A008 now while i am checking again i got the fault.

now it is working fine..

Thanks...

avik

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I dont think by change in time constraint will have an effect on percentage.

You can do a checking in PA side.

Ask your abaper to write codes for checking in your PA user exit.

EXIT_SAPFP50M_002.

In this exit,put a check for position,whether it is already occupied .

Regards,

Manoj.

Former Member
0 Kudos

Change the time constraint

This will not allow the gaps