Skip to Content
0
Former Member
May 27, 2008 at 06:34 AM

Issue regarding planned order generation.

39 Views

Hi PP experts,

I have a question, we have created a WBS element. That contains some finished materials. We have run the MRP for that WBS element with MD51 t-code. Then planned orders are not generated for some materials and generated for some materials. Even stock is not existed for those materials for which planned orders are not generated in planning run. MRP views are o.k. In stock requirements list,MD4C system is giving exceptional message for those materials, COVERAGE IS NOT PROVIDED BY MASTER PLAN (40). What would be the reason.

Thanks and regards

Vijay kola