My raw , semifinished products base unit of measure is in ton also finished product order & delivery also in ton. But I want to make finished product production in piece.

So what settings i want to do in customizing for to make production order in piece?

Company scenario is make to order.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member335796
Active Contributor
0 Kudos

Hi,

Production Unit of Measure in Work scheduling view and the Alternate Unit of Measure both needs to be maintained in Material Master.

Regards,

Siva

Former Member
0 Kudos

Hi,

In the work scheduling view of the material master maintain PC in the production Unit field

Regards,

SVP