May 27, 2008 at 05:02 AM

Reorganisation of PIR's related

37 Views

Hi pp legends,

I am tring to use the Reorganisation of PIR's (MD74) transaction for my requirement. for example, there is a requirement of 3000 nos for june and 2000 nos for july, if i run mrp, one planned order for 3000 and another planed order for 2000 is generated. after converting my planed order, i was able to produce only 2950, the remaining 50 nos is my loss. i cannot produce that odd 50, only this 2950 only will be sent to meet that 3000 nos requirement. next time if i run the mrp, the system is planning for the remaining 50 nos also which i dont want to plan. the requirement of 3000 has to get nullified with my actual output of 2950. for that i tried md74, there only PIR is only getting cancelled and the quantity produced for that requirement is being consumed for next orders.

If any body can help me in sorting out this problem, it will be of great use for me.

Thank you

regards,

senthil nathan.k