on 05-27-2008 6:00 AM
If customer cancelled his requirement for any of the products within a single sales order then how to prevent that product in MRP run?
We will have to keep history of sales order changes also in such case.
Hi,
In VA02 change of sales order , in item overview thereis a field MRP relevency. Select CN - NO planning in MRP. .
MRP will not consider this line item.
Active this status for the line item which customer has cancelled.
Regards
Amit Parkhi