After MRP run, if Sales order quantity is to be changed than what implication will planned order have in next MRP run?

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on May 27, 2008 at 05:13 AM

    Hi,

    If we change the sales order quantity, then there will not be any change in planned order unless we take MRP . After MRP the old planned orders will get deleted and new gets created with the new quantity in the sales order.

    Please maintain the run time parameter as "Deleteand Recreate "

    Regards

    Amit Parkhi

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 27, 2008 at 05:04 AM

    Hi MMV,

    When we run the MRP after changing the sales order qty, then the planned order quantity will be changed to the modified sales order qty.

    Thanks and regards

    murugesan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.