I have a question regarding earliest reclac date in IT 0003.

In pt60 to run time eval we give 2 dates i.e Time eval. from and to dates. While running time eval are the earl. recalculation date or pdc date taken into consideration?

So is there anything like earl. recalc date being picked up for the first time time eval is run (i.e when an perosn is hired) and pdc date being picked up there after?

Is IT0003 looked during time evaluation?

Thanks in advance,

Shruti.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 27, 2008 at 06:10 AM

    Hi,

    earliest retro date specifies the earliest date that can over be evaluated for that person.

    This date is also check when users try to record data in the past.

    E.g. earliest retro date is 01-01-2007. If user tries to record an absence on December 25, 2006, user will not be able to save the rabsence as it precedes the earliest retro date.

    Time Evaluation can never be processed before this date.

    PDC - date stores the date which should be the first date to be evaluated.

    E.g PDC-date currently is Jan. 15, 2007. If user records an absence for Jan. 7, 2007, PDC date will be set to Jan. 7 2007 as this date needs to be re-evaluated due to recording of the absence.

    If none of the dates in PT60 is recorded, SAP will automatically takes this date into account.

    Wilfred.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      1. If you do not give any start date while executing pt 60. The system will check the employee hire date and start from that date.

      2. Once you run time evaluation upto 30.06.2007 (live). When you are doing the time evalution next time and if you have not given start date (blank) the system automatically picks up the date as 01.07.2007 because the time evaluation for that employee already been done.

      If you want the system to recalculate the from past date, you have to give start date 01.06.2007 to end date.

      I think this is clear.

      Please reward points.

      Regards

      Venu

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.