Dear guru ,
I run MFBF with a REM Profile that post Automatic GR and Activities.
I have four operation in the material routing.
For the first three operations I want to confirm them with target activities.
I want to confirm only quantity without activities for the last operation.
I want to post Automatic GR and save material document (131) and target activities for the first three operation.
Subsequently I want to confirm actual activities only for the last operation.
How can I run this process ?
Thanks in advance.