Hi All,
I have come across one problem where MRP is behaving unexpectedly. Scenario is like
I have one FERT say 'A' with lot size procedure is FX and fix lot size is 1
In BOM of A there is another FERT 'B' with lot size proce FX and lot Size is 5
In BOM of B there is component say 'C' with lot size procedure 5 ( 5 day lot size procedure) and rounding value 3
When I create PIR for A say qty 5 for month of june and ran the MRP.
MRP shows the result in MD04 as follow:
5 diifferent plan ord. for 'A' with qty 1
1 planned order for 'B' with qty 5 and 5 depen. req. with qty 1
1 pur req for 'C' with qty 6 and 5 dep. req. with qty 1
I am expecting in comp. 'C' MRP should create 1 dep requ with qty 5 and not from the above case.
Please give me your valuble inputs.