Hi All,

I have come across one problem where MRP is behaving unexpectedly. Scenario is like

I have one FERT say 'A' with lot size procedure is FX and fix lot size is 1

In BOM of A there is another FERT 'B' with lot size proce FX and lot Size is 5

In BOM of B there is component say 'C' with lot size procedure 5 ( 5 day lot size procedure) and rounding value 3

When I create PIR for A say qty 5 for month of june and ran the MRP.

MRP shows the result in MD04 as follow:

5 diifferent plan ord. for 'A' with qty 1

1 planned order for 'B' with qty 5 and 5 depen. req. with qty 1

1 pur req for 'C' with qty 6 and 5 dep. req. with qty 1

I am expecting in comp. 'C' MRP should create 1 dep requ with qty 5 and not from the above case.