hi,
i would like to know how to map the scrap into system? user know the scrap qty. only after production.
suppose to produce 100 pcs of material 'A' , raw mtrl 1000 kg is issued. Actual consumption for 100 pcs is 990 kg and 10 kg is scrap.The consumption and scrap qty is not fixed.
Now during confirmation(co12) yield qty is 100 pcs but in scrap qty i cant put 10 kg as scrap.each time user have to convert it into pcs and the problem is to produce a single pc of A, the raw mtrl consumption is not fixed. so user have to calculate it from actual consumption and the production ord qty.
So how to map it and how to do the confirmation and GR of scrap?
In BOM, the scrap mtrl is maintained with -ve qty.
waiting for ur rply....
Rgds
Payel