Scheduling agreement

Dear All,

I am trying to create a Scheduling Agreement. But the problem is when I take either forecast or Jit delivery schedule, subsequent delivery is taking all the quantity. In my delivery schedule of same material I have mentioned 3 dates ( different). But when I am creating delivery with refernce to the scheduling agreement it is copying all the quanity into a single date. Can anyone tell me the reason?

Scheduling agreement is supposed to create different delivery schedule for the customer.

Thanks in Advance

Regards

Ashish

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    May 23, 2008 at 09:26 AM

    Hi Ashish

    one delivery different dates its not going to happen , do it one by one.

    one delivery give date again with ref sales order you can do it one more delivery with different date. like that do it and see

    i hope you have understod.

    if you get it don't forget to reward.

    thanks

    surya

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Surya,

      Thanks for your reply. Can you articulate in details as what you are trying suggest?

      Regards

      Ashish

  • May 23, 2008 at 06:58 PM

    Hi ashish

    Check the planning delivery schedule tab and go to item data -> delivery schedule header and check wheather any proper information has been filled or not

    Regards

    Srinath

    Add comment