Hello all.
We have created a small user status profile to be assigned to phases & tasks.
Later it will be assigned via BAPI, for now we assign it manually in the relevant project elements.
If we define the user status profile with status numbers & an initial status things work fine.
If we however define the profile without an initial status and only enter the profile (without manually setting a status) it seems the user status profile entered is lost (it is not there the next time you access that phase/task).
Is the standard behaviour? If yes, I assume it may be later be hard to default the a user status profile w/o status numbers/initial status.
Comments / experiences regarding this?
Regards / Anders
Edited by: Anders Loven on May 22, 2008 11:56 AM