Hi ,

I need to schedule a Meta Chain every two hour in day time. Requirement is that if process chain fails at any step of data load and overall status is 'RED' for that frequency let say(10 am), so the next load (at 12 pm) should not be start until unless the we resolve the previous error.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 24, 2018 at 01:35 PM

    Hi,

    You can create an ABAP program which checks the last run status of the process chain and triggers an event if it's a success.
    Then schedule the program individually or add it in a new process chain to run every 2 hours.
    Finally set your main PC's start variant to run based on the event that you raise in the ABAP program.

    Regards,
    Erdem

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 25, 2018 at 06:05 AM

    Hi,

    You can use the function BP_EVENT_RAISE in your ABAP program to trigger the event.