Hi Expert,

I need your help, We are using (no-time evaluation): Our client requires OT to be calculated based on employees working i.e

In Working days:

minimum 3 hours (xx amount) more than 3 upto 5 hours (yy amount)

In holidays:

minimum 3 hours (zz amount) more than 3 upto 5 hours (aa amount)

i have written pcr, its working fine for 1 day but two or more days system is addition days hours i.e (on 1st of jan 3 hours worked on 2nd of jan 5 hours worked now result is showing 8 hours and yy amount. how can we split dates of infotype 0015.

and how do we call holidays so that system can read holidays rate.