Intercompany STO Process with additional Stock Transfer between plants

Jan 24 at 07:27 AM

40

avatar image

Dear All,

Please find our scenario for Intercompany STO Process.

Company 1 = Stock exists

Company 2 = Delivery and Billing in Company 2

Company 3 = STO will be raised by Company 3

Company 3 raises an Intercompany STO always to Company 2 to supply the materials. Company 2 based on the STO requirement have to move the stock from Company 1 to Company 2. After stock moved, Company 2 will do the PGI and Intercompany Billing to Company 3.

My Question is how can i achieve the requirement of moving the stock from Company 1 Company 2 in between this Intercompany STO process.

Kindly advise.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Jürgen L
Jan 24 at 10:29 AM
0

A STO in SAP is between 2 parties only.

so you either need 2 STOs or you change your process and let C3 order at C1

Share
10 |10000 characters needed characters left characters exceeded
Jawad Ahmed Jan 25 at 01:17 PM
0

Dear Jurgen,

Is there any possibility or enhancement that before PGI of Outbound delivery we can use movement type 301 to move the stock first and then do the Post Goods Issue.

Thanks.