I am a PP Consultant, please solve my problem.

i create activity type in KL01 for setup labour and machine,

i had assign these activities in respective work centre with SAP005, 006 & 007 w r t cost centre.

In KP26 all the values are maintain for the month of may.

but when i do costing for material, it takes only raw material costing into account and other setup labour & machines values showing "0". i.e. system takes raw material value for sfg anf fg material though i maintain routing for all materials.